Construction Detail: Foundation Footings

Pete Sucheski

Jump Footing

1. Short Span The maximum allowable wall span between footings is 4 feet (for longer spans, consult an engineer).

2. Easy Jump The maximum difference in elevation for residential walls with discontinuous footings is 5 feet.

3. Reinforcing To enable the wall section to function as a beam, install two #4 steel reinforcing rods at the top and bottom (extending 3 feet into the main wall).

Where foundation footings change elevation, forming and pouring a continuous footing is problematic. But the ACI 332 standard referenced in recent codes allows short wall sections to span between discontinuous footings, within certain limits.


About the Author

Ted Cushman

Contributing editor Ted Cushman reports on the construction industry from Hartland, Vt.

Upcoming Events

  • How the Right Mortgage Platform Fuels Builder Growth Amid Affordability Pressures

    Live Webinar

    Register for Free
  • What 50,000 Home Builder Conversations Tell Us

    Live Webinar

    Register Now
  • The Next Evolution of Zonda Enterprise for Builders

    Webinar

    Register Now
All Events